We are moving forward with the Tesco Gerrards Cross development as quickly and as safely as possible in order to minimise any disruption to local people. Below is a list of milestones achieved to date and an indicative timeline of upcoming project milestones that we will be following to complete the project.
At each stage of the development various checks need to be carried out by Network Rail and relevant authorities; as these checks are completed we will progress to the subsequent stage of the project. This timeline - like any construction timeline - is subject to change; however we and our contractors, Costain will endeavour to keep this as up-to-date as possible so please check back for updates.
Previous Key Milestones
August 2007
- Reinforced Concrete Site Trials at Erith Commenced.
February 2008
Advanced Works Package Commenced. Consisting of:
- Mobilisation Activities
- Temporary Backfilling Over Crown of Tunnel Units
- Dismantling of Existing Steel Store Framing
- Installation of Temporary Bridge to Allow Plant Access Across the Railway Line
- Removal of Existing Steel Store Framing
March 2008
- Geodesign Site Investigation Works Commenced.
- Reinforced Concrete Site Trials at Erith Completed.
June 2008
- Advanced Works Package Completed.
July 2008
- Site Office Relocation Works Commenced and Completed.
- Geodesign Site Investigation Works Completed.
August 2008
- Ramp / Crane Platform Construction Works Commenced.
December 2008
- Contiguous Piled Wall Construction Works Commenced on Both North and South Side of Site.
- Network Rail Final Form B Approval for Permanent Works Completed.
January 2009
- Trackside Works Commenced.
February 2009
- Tunnel Unit Installation Works to Collapse Zone Commenced.
- Ramp / Crane Platform Construction Works Completed.
March 2009
- West Portal Works Commenced.
- Bulk Earthworks Commenced.
- Bridging Slab Works at Packhorse Road Site Entrance Commenced.
April 2009
- Tunnel Arch Reinforced Concrete Surround Works Commenced.
- East Portal Works Commenced.
- Tunnel Unit Installation Works to Collapse Zone Completed.
May 2009
- Bridging Slab Works at Packhorse Road Site Entrance Completed.
June 2009
- Crawler Crane Demobilisation Works Commenced.
- Goliath Crane Erection and Commissioning Works Commenced and Completed.
July 2009
- Crawler Crane Demobilisation Works Completed.
- Contiguous Piled Wall Construction Works Completed on Both North and South Side of Site.
September 2009
- ‘Block 5’ Reinforced Concrete Arch Structure Works Commenced.
November 2009
- Tunnel Foam Concrete Works Commenced.
- ‘Block 5’ Reinforced Concrete Arch Structure Works Completed.
December 2009
- Tunnel Backfill & Capping Works over Foam Concrete Commenced.
April 2010
- Importation of Aggregate to Site Using Conveyor System Commenced and Completed. Conveyor Use Ceased.
- Goliath Crane Demobilisation Works Commenced and Completed.
May 2010
- Packhorse Road Bridge Footway Works Commenced.
- Tunnel Arch Reinforced Concrete Surround Works Completed.
- Conveyor Removal Works Commenced and Completed.
Upcoming Key Milestones
June 2010
- Packhorse Road Bridge Carriageway Works Commence.
- Tesco Store Car Park Works Commence.
- Tesco Store Construction Works Commence.
- Tunnel Foam Concrete Works Complete.
- West Portal Works Complete.
- Tunnel Backfill & Capping Works over Foam Concrete Complete.
August 2010
- Trackside Works Complete.
September 2010
- East Portal Works Complete.
November 2010
- Tesco Store Car Park Works Complete.
- Packhorse Road Bridge Footway Works Complete.
- Packhorse Road Bridge Carriageway Works Complete.
- Tesco Store Construction Works Complete.
November/December 2010
- Gerrards Cross Tesco Store to Open.
|